YENA has long term lease contracts with 11 factories.
YENA Welding engineers have full control on the procedures and the fabrications.
No.
We are flexible with order sizes.
In 2019 we had contracts between 1000 € to 1,050,000 €.
For each project YENA assigns a project manager, and a QAE. ( quality assurance engineer)
The QAE works in the factory full time during the project.
YENA engineers can support our client to draft an ITP based on the project.
However final ITP should be approved by the client.
We have 2 full time IWE, 2 contracted IWE and there are 7 welding engineers working in the contracted factories.
Yes, we also can serve our clients with design services. (TEKLA, STATICA and ACAD.)
This varies on each project, as an example : Yena managed to engineer, produce and deliver the products within a 20 days delivery term for a very urgent project of a tank terminal in Amsterdam.
3 days – TEKLA layouts & fabrication drawings.
2 days – material procurement
8 days – Steel fabrication
2 days- Galvanizing
5 days- Truck delivery and Customs operations in Netherlands.