Galvanised Structural Steel Racks Manufacturing

Client

One of the biggest construction companies in the Netherlands.

Scope

Structural steel fabrication including coating

Volume

350 Tons

Details of the Pipe Supports Project

Final Usage

The parts were manufactured for a reefer racks project.

Specifications

S235JR, S275JR, S355J2H steel grades was used for the project. Total volume was 350 tons. Maximum lenght of one piece was 12,8 meters and maximum weight of one piece was 2,6 tons.

Coating

Hot dip galvanising applied.

Project Scope

Scope of the project includes  Raw Material, Fabrication, QA/QC, coating, and transportation to site.

All part were delivered as the client requested .

In November 2019, Yena completed the fabrication and shipment of Structural Steel Reefer Racks with success. The project was 350 tons in total.

Project scope for Yena was purchasing of raw materials, fabrication according to building shopdrawings, galvanisation, packaging and shipment to customer site in Netherlands.

Material grades were S235JR, S275J2 and S355J2H. All manufacturing and galvanisation were done in Turkey facilities and controlled by Yena engineers. Project was completed in 1 month include with shipment.

Fabrication standard was EN 1090-1 EXC2 and galvanisation done according to EN 1461. Shipments were completed by roadway truck shipments, in final 22 trucks shipped all project goods.